Worked example · Supplier delivery exceptions

A pilot, week by week.

Six weeks at a sample manufacturer with four buyers and a planner: the baseline, the setup, what the team worked live, and the readout that decided whether to go ahead.

A composite, illustrative scenario. These are not LevelOneAI customer results.

Before day one

The baseline

Taken from the last quarter and signed with the success criteria: catch supplier changes earlier, and cut expedites and late customer shipments caused by suppliers.

Open POs
142
Supplier changes a week
About 25
Expedites last quarter
9, about $61,000 in premium freight
Line stops waiting on parts
2, 14 hours
Customer shipments late because of suppliers
6
Warning before the need date
About 1 day

Weeks 1–2

Setup, from the pilot kit

During setup, the team established its operational data sources, exception criteria, ownership rules and approval requirements. The workflow was tested against representative scenarios on the plant's own data before going live.

See the pilot kit

Weeks 3–6

The team works real exceptions

  1. Week 3

    PO 4512 caught on the day it moved

    Ridgeway moved the date from Oct 12 to Oct 26. Operations Resolution connected it to run A-88 on Oct 20 and two customer orders worth $214K, and opened an item for the buyer the same morning.

  2. Week 3

    A split shipment instead of an expedite

    The buyer asked for 60 housings by Oct 19. The planner approved it, and the item stayed open until the parts were received.

  3. Week 4

    A vague reply didn't close the item

    "Working on recovery, will confirm Monday" isn't a date, so the item stayed open and the fallback went for approval six days before the need date.

End of week 6

The readout

Problems prevented come first, and they're reported separately from how the work changed. A result only counts where the Operations Resolution flagged the problem first.

Business outcomes

Problems flagged before anyone acted
11
Resolved before the need date
9 of 11
Expedites in the 4 live weeks
1, against a baseline pace of 3
Customer shipments late because of suppliers
1, against a baseline pace of 2

How the work changed

Exceptions with the impact assembled automatically
87%
Time from a supplier change to a decision
3.1 days → 0.6 days

Decision: go

The success criteria were met, so the pilot became phase 1 of Operations Resolution. What the team confirmed during the pilot carried straight over, and the pilot fee was credited to setup.

Illustrative composite scenario · sample company and figures